In mine excavation and tunnel construction, the core pain points of rapid loss of picks and slow footage penetration are mostly not problems with pick quality or operation, but insufficient matching between the number of cannon heads and picks – too much or too little will delay the construction period and increase costs. Accurate matching is the key to efficient construction.
This article focuses on the core points, skips redundant theories, and only talks about the matching methods, steps and pitfall avoidance skills necessary for first-line practical operation, so that novices can get started quickly!

1. Core premise: Understand the two keys and do not blindly match them
The core of matching the number of picks is “adapting to working conditions + fitting the nozzle”. There is no need for complicated calculations. First, clarify two basic premises to avoid detours:
Cannon head parameters (bottom line): Based on the “rated number of picks” marked in the tunnel boring machine manual, it does not exceed the maximum load capacity and is not less than the minimum safety value (such as the 260 fully mechanized excavator, the rated number of picks is usually 42-48). Different manufacturers have different cannon head designs, so check the manual first.
Rock layer hardness (core): Three types of working conditions are divided according to the f value, which directly determines the adjustment direction of the number of picks (key note): soft rock (f ≤ 3), medium hard rock (3 < f ≤ 6), and hard rock (f > 6). Subsequent matching is centered around these three types of working conditions.

2. Key practical operations: 4 steps to match the number of picks (direct use for novices)
This is the core of this article. Follow the steps to achieve accurate matching without professional skills, taking into account both efficiency and cost:
The first step: clarify the basic parameters
Confirm two key pieces of information: ① The rated number of picks in the gun head (check the instruction manual); ② The f value of the on-site rock formation (geological report or trial tunneling judgment). This is the prerequisite for matching and does not need to be adjusted blindly.
Step 2: Determine the baseline quantity
Based on the rated quantity, adjust according to the hardness of the rock layer (remember this ratio, no additional calculation is required): 1. Soft rock working conditions: reduce by 5%-10% (to avoid mud pockets, increase footage); 2. Medium hard rock working conditions: maintain the baseline quantity (taking into account both efficiency and durability); 3. Hard rock working conditions: increase by 5%-15% (distribute stress, reduce tooth chipping). Example: Rated 45 picks, 40-42 picks for soft rock, 48-52 picks for hard rock.

Step Three: Simple Optimization Selection
After the quantity is determined, it is necessary to cooperate with the selection skills of reasonable pick arrangement to ensure professional adaptation and extend the life of the picks. First, let’s clarify the core pick arrangement principle: The picks of the tunnel boring machine are arranged in spirals (the mainstream is 2-3 spirals). The core purpose of the arrangement is to make the picks “staggered peak cutting” – the picks of adjacent spiral lines are staggered with each other to avoid the same section being stressed at the same time, disperse the rock-breaking load, and at the same time ensure smooth chip removal, and reduce the interference between “mud-packed picks” and picks. Based on this principle, two practical skills are used: ① Use the enhanced wear-resistant type for the edge picks (easiest to wear and bear the greatest force), and use the standard type for the inner ring; ② Use pointed picks for soft rock, and use blunt-headed heavy-duty picks for hard rock. There is no need to complicatedly adjust the arrangement density, and efficient cutting can be achieved by following the fitting principle.
Step 4: On-site commissioning (key step)
Trial tunneling for 1-2 hours, and observe three indicators for fine-tuning: ① The pick wears quickly → increase the quantity appropriately; ② The footage is slow → reduce the quantity appropriately; ③ The equipment vibrates greatly → check the quantity or the fit of the gear seat.

3. Avoid high-frequency pitfalls: 4 misunderstandings, 90% of people have stepped on them
To avoid these misunderstandings, directly reduce pick loss and improve efficiency, focus on remembering and checking yourself regularly:
Myth 1: “More picks are more durable”
Wrong: Too many picks will interfere with each other, repeat cutting, increase resistance and energy consumption, and cause more uneven wear; Correct: Control within a reasonable range according to the rock formation and gun head parameters, and do not blindly increase the amount.
Misunderstanding 2: “Save costs by installing fewer picks”
Wrong: The force on a single pick doubles, which makes the tooth prone to chipping and frequent shutdowns, which in turn increases the cost of consumables and construction period; Correct: not lower than the minimum value in the instruction manual, and dynamically adjusted according to working conditions.
Misunderstanding 3: “One quantity applies to all working conditions”
Wrong: Soft rock requires fewer teeth for high efficiency, while hard rock requires more teeth for impact resistance. A fixed number will lead to batch scrapping of picks or slow footage advancement; Correct: When working conditions change, the number of picks is adjusted synchronously.
Misunderstanding 4: “Only adjust the quantity and ignore the gear seat”
Wrong: The gear seat is worn and deformed. Even if the number matches, the picks will be unevenly stressed and their lifespan will drop sharply. Correct: Check the tooth seat before matching, clean the debris, and replace the worn tooth seat.
4. Key maintenance: 2 actions to extend matching life

After accurate matching, do two points of maintenance to further reduce costs and increase efficiency:
Inspection per shift: Confirm that the number of picks is complete and evenly worn, timely replace broken teeth, replace missing picks, and simultaneously check the status of the gear seat.
Standard operation: increase the rotation speed and reduce the propulsion force for soft rock, and vice versa for hard rock to avoid idling of the nozzle and hard top rock, and reduce unnecessary losses.
Conclusion
There is no complicated theory required to match the number of nozzle picks. By focusing on the three key points of “base quantity + rock layer adjustment + pit avoidance maintenance”, efficient excavation, cost reduction and efficiency improvement can be achieved.